Wrapped furniture on steel racking in a consolidation store


Mardna Talvik



Status update



Procurement tracker, week 24



Updated

16 June 2027

Lines ordered

151 of 214

Install starts

4 October 2027

Your decision

One, by 21 June

Wrapped furniture on steel racking in a consolidation store

Status at week 24



Read from the live FF&E tracker on 16 June. All values in EUR, excluding VAT. The tracker link stays current, and this page is the summary we send every second Wednesday.




0



Lines ordered of 214


0



Lines delivered to store


€0



Committed of €486,500


0



Line at risk

One supplier has slipped five weeks. The lounge chairs now land after install starts, and that is the only line that can move opening.

Where the money and the lines are



From the live tracker, 16 June 2027. Committed spend is 72% of budget with 71% of lines ordered, so the remaining lines carry no cost surprise so far.



Committed by category, € thousand

Total €351.3k against a €486.5k budget, contingency included

Committed by category, € thousand

Status of 214 lines

Delivered means received and checked at the store

Delivered
38 (18%)
In production
94 (44%)
Awaiting confirmation
19 (9%)
Not yet ordered
63 (29%)

Lead times against the 4 October install



Every order date, lead time and delivery is drawn from supplier confirmations. Item codes and PO numbers sit in the tracker. Only the lounge chair line crosses the install date.



DayWeekMonthQuarterSemesterYear
M5May
M6Jun
M7Jul
M8Aug
M9Sep
M10Oct
M11Nov
Beds and casegoods, 12 weeks
Joinery, 12 weeks
Lighting, 9 weeks
Lounge chairs, 22 weeks, at risk
Textile orders close
Textiles, 8 weeks
Consolidate at store
Install, 38 units
Snag list
ProductionMay 3 - Jul 23

Beds and casegoods, 12 weeks



ProductionMay 24 - Aug 13

Joinery, 12 weeks



ProductionJun 7 - Aug 6

Lighting, 9 weeks



ProductionMay 17 - Oct 15

Lounge chairs, 22 weeks, at risk



To orderJun 28 - Jul 9

Textile orders close



To orderJul 12 - Sep 3

Textiles, 8 weeks



LogisticsAug 16 - Sep 24

Consolidate at store



Install4 - Oct 22

Install, 38 units



Install25 - Oct 29

Snag list



How a line moves through the tracker



Every one of the 214 lines passes through the same five states. The date beside each state in the tracker is the one the supplier confirmed in writing.



Specified

Finish, quantity, net price and supplier are locked in the schedule, and you've signed that group of lines off.

Ordered

We issue the purchase order and pay the deposit. The supplier has three working days to confirm a dispatch date.

In production

Rasmus checks progress at weeks 4 and 8 of any lead time over 10 weeks, with factory photos logged against the line.

Delivered to store

Received at our Ülemiste store, unpacked and checked against the specification within two working days. Damage goes back the same week.

Installed

Placed in its unit and closed off on the snag list. A line isn't finished until Kadri's team has signed that unit over.

Status by zone



Open a zone to see where it stands. Line counts add up to the 214 in the tracker.



Studios, 26 units

122 lines, 96 ordered. Beds and wardrobes are in production and due at store on 26 July. Desk lamps ordered last week. On plan.


Aparthotel studio with oak bed and wardrobe joinery

One-bed suites, 12 units

58 lines, 41 ordered. Sofa beds confirmed at 12 weeks. Curtains go out with the textile order by 9 July. On plan.


Suite living area with a wool sofa bed and sheer curtains

Lobby and lounge

24 lines, 8 ordered. The 18 lounge chairs are the line at risk. Reception joinery is on plan, and the decision below settles the rest of this zone.


Hotel lobby lounge with low oak tables

Café

10 lines, 6 ordered. Bar stools came in at €1,140 under budget. Pendants are on plan, with delivery to store on 9 August.


Cafe with oak bar counter, steel stools and pendants

Risks, access and contingency



The things we are watching. Each has an owner and a date in the tracker, and none has reached the budget yet.



Why the lounge chairs slipped

The maker lost a foam supplier in May and has moved production to a second plant. Written confirmation now reads 15 October, against 10 September in the order. We have asked for a cost-free cancellation window until 25 June, which they have accepted.

Contingency, what's left

The €486,500 budget holds €44,227 of contingency. None has been drawn so far. The substitution below would add €2,360 back to it.

Freight and customs

Three containers come from outside the EU, and clearance is covered in each landed price. We've allowed nine working days from port to store at Muuga. A longer hold moves the store date, not install, until 24 September.

Access at the harbour site

The main contractor releases floors in sequence from 4 October. Goods lift booking is 07:00 to 15:00, and two loading bays are shared with the fit-out trades. Rasmus holds the weekly slot list.

Deposits and changes

Deposits on made-to-order lines average 40%. A change after order loses the deposit and restarts the lead time, which we'd flag here before you decide.

One decision, by Monday 21 June



We recommend the substitution. Same wool, same seat height, a slightly narrower arm, sample at your office from Thursday. If you keep the original, the lobby opens with rented seating until the chairs arrive on 15 October.



Prepared by



Rasmus Talvik Project director, Mardna Talvik

Telliskivi 42, 10611 Tallinn rasmus@mardnatalvik.ee

For approval by



Kadri Tamm General manager, Lumi Harbour

Next tracker update: Wednesday 30 June 2027.

Approved
Slide to approve
En approuvant ce document, vous le signez électroniquement.

Approve the lounge chair substitution

By confirming, you approve replacing the 18 lounge chairs with the alternative from the Finnish workshop, at €2,360 less overall and delivery to store on 13 September 2027. We will cancel the original order by 25 June at no cost.