Vidal Ortúzar Arquitectos mark



Hotel Almenar · Site report 7



Three weeks behind, recoverable, and one decision needed.



Status at 3 September 2027



Report 7, for Beatriz Almenar. The figures come from the contractor's seventh valuation, which we checked against the site on 1 September.




0%



Complete, plan was 51%


0



Weeks behind programme


€0.00m



Forecast, contract €9.48m


0



Lost-time incidents

The timber arrived three weeks late, and every trade above level three now waits on it. Handover on 31 March 2028 still holds.
TThhee ttiimmbbeerr aarrrriivveedd tthhrreeee wweeeekkss llaattee,, aanndd eevveerryy ttrraaddee aabboovvee lleevveell tthhrreeee nnooww wwaaiittss oonn iitt.. HHaannddoovveerr oonn 3311 MMaarrcchh 22002288 ssttiillll hhoollddss..

Progress against plan



Cumulative percent complete by value. The gap opened in June, when the first timber delivery slipped, and it has held steady at five points since July.



Planned, percent complete

Baseline programme, rev 2

Planned, percent complete

Actual, percent complete

Contractor valuations 2 to 7

Actual, percent complete

Level 3, timber floor down

The first of the cross-laminated floors, set on the concrete podium, gives you the true ceiling height of the guest rooms for the first time. It reads lower and calmer than the model suggested, which we think is a gain.


Cross laminated timber ceiling on concrete columns in evening sun

The courtyard, open to the sky

The void is now legible at full height. Its deep shade at 17:00 in September confirms the sun study, and it is the first place on site where you can feel what the building is trying to do.


Looking up through a concrete courtyard void to bright sky

Facade sample, west elevation

A full-height sample of the proposed ceramic lattice stands on the west side, so you can judge it in the same light as the finished rooms. This is the sample the decision below refers to.


Terracotta ceramic lattice sample casting patterned shadow

The next five weeks



From Monday 6 September to report 8 on Friday 8 October. Timber on levels 4 and 5 is the work that decides whether the recovery holds.



DayWeekMonthQuarterSemesterYear
W3630 Aug
W376 Sep
W3813 Sep
W3920 Sep
W4027 Sep
W414 Oct
W4211 Oct
W4318 Oct
W4425 Oct
Services first fix, levels 1 to 3
Timber delivery, levels 4 and 5
Your facade decision
Timber erection, two shifts
Roof waterproofing begins
Report 8 issued
ServicesSep 6 - Oct 8

Services first fix, levels 1 to 3



Timber13 - Sep 24

Timber delivery, levels 4 and 5



Decision24 - Sep 25

Your facade decision



TimberSep 20 - Oct 22

Timber erection, two shifts



Roof4 - Oct 8

Roof waterproofing begins



Report8 - Oct 9

Report 8 issued



How the three weeks come back



The contractor's plan, which we reviewed and accepted on 2 September at no cost to you. It leaves little slack before Christmas.



Second crane shift, from 20 September

Timber erection runs two shifts until level 5 closes, which recovers about nine working days.

Facades start on the east

Scaffold is struck on the courtyard side first, so glazing can start before the roof is complete. That recovers about five days.

Fit-out starts at level 1

Guest room fit-out works upward, as planned, but with two crews from November. It absorbs the rest.

New baseline, Friday 5 November

We report against the recovered programme from report 9. If the gap hasn't closed by then, we will say so and tell you what it does to the handover.

Risks, and the decision we need



In order of how much they could cost you. We've kept the list short because most of what we could list would not change anything you do.



Decision: facade shading, by Friday 24 September

The specified aluminium fin supplier has moved its lead time to 22 weeks, which would miss the handover. We propose the ceramic lattice now on site as a sample, made in Andalusia, with a 9 week lead time. It adds €38,260 plus IVA, already in the forecast.

Risk: timber erection falls behind again

Likelihood medium, effect high. A second late delivery would use all the recovery and move the handover by up to three weeks, past the Feria de Abril. The supplier has confirmed the September dates in writing. We inspect the load at their yard on 8 September.

Risk: forecast above contract

€140,000 over contract, or 1.5 percent: ground conditions at the northern basement wall, which we reported in report 3, plus the shading above. The contingency of €190,000 covers it. A further €50,000 remains.

Not a risk any more

The electrical connection date is confirmed for 17 January 2028. It has been on this list since report 2, and we are glad to remove it.

One decision, by Friday 24 September



Come and stand in front of the sample at 18:00, when the west light is on it. If you would rather keep the aluminium, tell Marta. We will reprice the programme with its 22 week lead time before anything is ordered.



Prepared by



Marta Ortúzar Partner, Vidal Ortúzar Arquitectos

Calle Feria Nueva 18 41003 Sevilla marta@vidalortuzar.es

For approval by



Beatriz Almenar Owner, Hotel Almenar

Next report: Friday 8 October 2027

Approved
Slide to approve
En approuvant ce document, vous le signez électroniquement.

Approve the ceramic lattice

By confirming, you approve the ceramic lattice in place of the specified aluminium fins on the west and south elevations, at an added €38,260 plus IVA. We will instruct the contractor to order it by Monday 27 September 2027.