Fee variation V2
Adding the recording suite
Akademie Neue Klänge, rehearsal building. Decision needed by Friday 4 June 2027: make this change, or keep the current scope.

A new room below the hall
On 10 May, Clara Wieser asked us to add a 186 m² recording suite beneath the main rehearsal hall.
The appointment of 18 January covers a rehearsal building with a plant basement. A new donor agreement now funds recording facilities.
The room needs its own floated structure, so the basement slab, part of the frame and the services routes all change. Stage work done so far stands. This page prices the change only.
The impact
Four numbers, each measured against the current scope.
+€0
Our fee, excluding USt
+€0
Estimated build cost
+0
Weeks to permit submission
+0 m²
Gross floor area
The change, priced
EUR, plus 20 percent USt. Built from our agreed hourly rates. This is additional to the appointment fee, which does not change.
Variation V2
Fixed for the scope above, if approved by 4 June.
Variation V2
Fixed for the scope above, if approved by 4 June.
Basement and structure redesign
Floated slab, frame changes, model update.
Acoustic consultant coordination
Our time only. The consultant is your appointment.
Services coordination
Ventilation and power routes through the new suite.
Amended permit drawings
Updates to the Einreichplanung set.
Project management
Seven weeks at the current rate.
Optional add-ons
Your choice. None of these is needed for the permit.
Optional add-ons
Your choice. None of these is needed for the permit.
Isolation mock-up review
One site session at the floor supplier's test rig.
VR listening walkthrough
Auralised model of the suite, one session.
Early contractor pricing
Room-in-room package priced before tender.
If you approve
Three steps, in this order.
Acoustic consultant appointed, by 4 June
Your appointment. We need their brief for isolation and background noise before the slab is redrawn.
Redesign starts, Monday 7 June
Structure first, then services. The other rooms stay as drawn.
Permit submission, Monday 9 August
The amended Einreichplanung goes to the Baubehörde five weeks later than the current 5 July date.
Revised programme
With the variation. The permit date moves by five weeks and tender documents by four. Site start stays in spring 2028. We plan for 12 weeks at the Baubehörde, and that period is outside our control.
Structure redesign
Acoustic design
Services coordination
Cost check
Permit submission
Baubehörde period
Tender documents
Assumptions, and what stays the same
What the price rests on, and what happens if you say no.
What stays the same
The appointment fee and the rest of the design. The hall, foyer and teaching rooms are not redrawn. Payment terms stay at 14 days.
If you don't make this change
We continue on the current scope, with no fee change and the 5 July submission date intact. The basement stays a plant room. Adding the suite after the slab is cast would mean underpinning. We estimate at least €190,000 more in build cost.
What this price assumes
One suite of 186 m², one control room, one isolation booth. One round of client comments. An acoustic consultant in place by 4 June.
What it excludes
Acoustic consultant and structural engineer fees, recording equipment, permit fees and any donor reporting.
Build cost estimate
€412,600 is the quantity surveyor's estimate at ±10 percent, dated 21 May. It is not a tender price. The cost check in July updates it.
Your decision, by Friday 4 June
To go ahead, approve below. To keep the current scope, reply to Theresa with one line. We need nothing else, and the 5 July date stands.
Prepared by
Theresa Aigner Partner, Aigner Reisch Architekten
Müllner Hauptstraße 12 5020 Salzburg theresa@aignerreisch.at
For approval by
Clara Wieser Managing Director, Akademie Neue Klänge
Rehearsal building, variation V2
Approve variation V2
By confirming, you instruct variation V2: a fee of €38,740 plus 20 percent USt and any add-ons selected above, a redesign start on Monday 7 June 2027 and a permit submission on Monday 9 August 2027.