Made with Formlio


Concrete and oak recording room with one strip of light


Aigner Reisch Architekten mark





Fee variation V2



Adding the recording suite



Akademie Neue Klänge, rehearsal building. Decision needed by Friday 4 June 2027: make this change, or keep the current scope.



Concrete and oak recording room with one strip of light
What changed



A new room below the hall



On 10 May, Clara Wieser asked us to add a 186 m² recording suite beneath the main rehearsal hall.



The appointment of 18 January covers a rehearsal building with a plant basement. A new donor agreement now funds recording facilities.

The room needs its own floated structure, so the basement slab, part of the frame and the services routes all change. Stage work done so far stands. This page prices the change only.

The impact



Four numbers, each measured against the current scope.




+€0



Our fee, excluding USt


+€0



Estimated build cost


+0



Weeks to permit submission


+0 m²



Gross floor area

Both answers are workable. Adding the suite now costs less than adding it later, and leaving it out costs nothing today.

The change, priced



EUR, plus 20 percent USt. Built from our agreed hourly rates. This is additional to the appointment fee, which does not change.





Variation V2

Fixed for the scope above, if approved by 4 June.

Total
$38740.00

Variation V2

Fixed for the scope above, if approved by 4 June.

Item
Price
Quantity
Total

Basement and structure redesign

Floated slab, frame changes, model update.



$14280.00

Acoustic consultant coordination

Our time only. The consultant is your appointment.



$5460.00

Services coordination

Ventilation and power routes through the new suite.



$7920.00

Amended permit drawings

Updates to the Einreichplanung set.



$6180.00

Project management

Seven weeks at the current rate.



$4900.00
Total
$38740.00

Optional add-ons

Your choice. None of these is needed for the permit.

Total
$0.00

Optional add-ons

Your choice. None of these is needed for the permit.

Item
Price
Quantity
Total

Isolation mock-up review

One site session at the floor supplier's test rig.



$3260.00

VR listening walkthrough

Auralised model of the suite, one session.



$2480.00

Early contractor pricing

Room-in-room package priced before tender.



$1940.00
Total
$0.00





Subtotal
$38740.00
Total (before tax)
$38740.00
USt (20%)
$7748.00
Total
$46488.00

If you approve



Three steps, in this order.



Acoustic consultant appointed, by 4 June

Your appointment. We need their brief for isolation and background noise before the slab is redrawn.

Redesign starts, Monday 7 June

Structure first, then services. The other rooms stay as drawn.

Permit submission, Monday 9 August

The amended Einreichplanung goes to the Baubehörde five weeks later than the current 5 July date.

Revised programme



With the variation. The permit date moves by five weeks and tender documents by four. Site start stays in spring 2028. We plan for 12 weeks at the Baubehörde, and that period is outside our control.



DayWeekMonthQuarterSemesterYear
M6Jun
M7Jul
M8Aug
M9Sep
M10Oct
M11Nov
M12Dec
Structure redesign
Acoustic design
Services coordination
Cost check
Permit submission
Baubehörde period
Tender documents
DesignJun 7 - Jul 2

Structure redesign



DesignJun 7 - Jul 16

Acoustic design



DesignJun 21 - Jul 30

Services coordination



DesignJul 26 - Aug 6

Cost check



Permit9 - Aug 10

Permit submission



PermitAug 10 - Nov 2

Baubehörde period



TenderSep 13 - Nov 26

Tender documents



Assumptions, and what stays the same



What the price rests on, and what happens if you say no.



What stays the same

The appointment fee and the rest of the design. The hall, foyer and teaching rooms are not redrawn. Payment terms stay at 14 days.

If you don't make this change

We continue on the current scope, with no fee change and the 5 July submission date intact. The basement stays a plant room. Adding the suite after the slab is cast would mean underpinning. We estimate at least €190,000 more in build cost.

What this price assumes

One suite of 186 m², one control room, one isolation booth. One round of client comments. An acoustic consultant in place by 4 June.

What it excludes

Acoustic consultant and structural engineer fees, recording equipment, permit fees and any donor reporting.

Build cost estimate

€412,600 is the quantity surveyor's estimate at ±10 percent, dated 21 May. It is not a tender price. The cost check in July updates it.

Your decision, by Friday 4 June



To go ahead, approve below. To keep the current scope, reply to Theresa with one line. We need nothing else, and the 5 July date stands.



Prepared by



Theresa Aigner Partner, Aigner Reisch Architekten

Müllner Hauptstraße 12 5020 Salzburg theresa@aignerreisch.at

For approval by



Clara Wieser Managing Director, Akademie Neue Klänge

Rehearsal building, variation V2

Approved
Slide to approve
En approuvant ce document, vous le signez électroniquement.

Approve variation V2

By confirming, you instruct variation V2: a fee of €38,740 plus 20 percent USt and any add-ons selected above, a redesign start on Monday 7 June 2027 and a permit submission on Monday 9 August 2027.