# Siège Halden Ionics : validation RIBA étape 3, conception rév. C

## Stage 3 sign-off

### RIBA Stage 3 sign-off

*Halden Ionics headquarters*

- You approve: Spatial coordination, rev C

- Sign by: Friday 17 September 2027

- It unlocks: Stage 4, from 27 September

- Approver: Dr Anneke Rowsell, COO

*Mass timber research building at dusk*

*Threadgold Mwangi Architects mark*

## What you are approving

*The decision*

The coordinated design at revision C: a 3,164 m² mass timber headquarters and battery materials lab, at a construction cost of £11.84m.

**If you sign by 17 September**, Stage 4 starts on 27 September, the planning application goes in on 1 October and the structural frame order can be placed in April 2028.

**If you don't**, Stage 4 waits. Each week of delay moves the frame order by a week, and past 29 October we lose the contractor's early engagement slot and the 2028 site start with it.

## The design at rev C

### The design at revision C

Views from the federated model as of 3 September. Open the live link in the project space to walk it before you sign.

*Mass timber laboratory floor with service spines*

*Timber stair in a four storey atrium*

*Glulam column and steel connector detail*

*Glazed facade modules with timber fins*

*Roof with solar panels and plant enclosure*

## What changed

### What changed since rev B

Measured against the review of 2 July. The second clean room caused the area and cost increases. The carbon fall comes from replacing the concrete core.

### GIA, up 64 m²

**3,164 m²**

### Cost, up £186k

**£11.84m**

### kgCO2e/m², down 38

**498**

### Open hard clashes

**0**

## The one thing

After this signature, moving a column costs a redesign of three packages. Moving a bench costs an afternoon. We've written down which is which.

## Fixed and movable

### What is fixed, and what can still move

Stated per system. Changes to fixed items after signature go through the change procedure in our appointment, with a cost and date attached before any work starts.

### Fixed after signature

Structural grid at 7.5 m by 9 m. Floor to floor at 4.2 m on lab levels and 3.6 m on office levels. Core and riser positions. Facade module at 1.5 m. Clean room location and its 450 mm raised floor.

### Movable until 14 January 2028

Lab bench layouts, fume cupboard positions within the service spines, equipment loads up to 5 kN/m², and room data sheets. After the freeze on 14 January these become change items.

### Movable until tender

Finishes, loose furniture, signage, reception joinery and the planting scheme. None of these touches the coordinated model.

### Risks you carry with this approval

Planning. We rate the application as supportable after two pre-application meetings, and no architect can promise consent. The determination period for a major application is 13 weeks. Stage 4 proceeds at risk during that period, and its fee is payable if consent is refused.

### Not part of this approval

Consultant appointments stay with you: structural engineer, M&E consultant, quantity surveyor and principal designer under CDM 2015. Planning and building control fees are also yours. Our fee stays as appointed under the RIBA Standard Professional Services Contract.

## When you sign

### The two weeks after you sign

Four actions in the two weeks after your signature. Nothing else needs you until the room data freeze.

### 1. Rev C locked, same day

Joel Prenderby marks the model as the coordinated baseline and issues it to all consultants.

### 2. Consultants instructed, 20 September

Structural engineer and M&E consultant receive their Stage 4 instructions, against the signed baseline.

### 3. Stage 4 kickoff, 27 September

A weekly coordination meeting starts, with the clash report published every Friday in your project space.

### 4. Planning application, 1 October

Design and Access Statement, drawings and the energy statement go in through the Planning Portal.

## Stage 4 programme

### Stage 4 and tender

Twenty-seven weeks from signature to contractor's return. The 13-week planning determination runs in parallel and is the one date we can't control.

| Task | Start | End | Duration | Label |
| --- | --- | --- | --- | --- |
| Planning submission | 2027-10-01 | 2027-10-02 | 5 days | Planning |
| Determination, 13 weeks | 2027-10-04 | 2028-01-03 | 5 days | Planning |
| Structural coordination | 2027-09-27 | 2027-11-19 | 5 days | Stage 4 |
| Facade package | 2027-10-11 | 2027-12-17 | 5 days | Stage 4 |
| M&E and clean room package | 2027-10-04 | 2028-01-21 | 5 days | Stage 4 |
| Room data sheet freeze | 2028-01-14 | 2028-01-15 | 5 days | Stage 4 |
| Tender package issued | 2028-01-31 | 2028-02-01 | 5 days | Tender |
| Two-stage JCT tender | 2028-02-01 | 2028-03-24 | 5 days | Tender |

## Sign-off

### Signature by Friday 17 September

If anything in revision C is wrong, tell Joel before you sign. A correction this week costs hours. The same correction in December costs a package reissue.

### Prepared by

**Wanjiru Mwangi**
Director, Threadgold Mwangi Architects

12 Osney Mead Yard
Oxford OX2 0ES
wanjiru@threadgoldmwangi.co.uk

### For approval by

**Dr Anneke Rowsell**
Chief Operating Officer, Halden Ionics

Project architect: Joel Prenderby
joel@threadgoldmwangi.co.uk

### Sign off RIBA Stage 3

By signing, you approve the Stage 3 design at revision C: 3,164 m² GIA and a construction cost of £11.84m excluding VAT. You also instruct Stage 4 from Monday 27 September 2027 and the planning submission on 1 October 2027.