Halden Ionics headquarters



RIBA Stage 3 sign-off



You approve

Spatial coordination, rev C

Sign by

Friday 17 September 2027

It unlocks

Stage 4, from 27 September

Approver

Dr Anneke Rowsell, COO

The decision



What you are approving



The coordinated design at revision C: a 3,164 m² mass timber headquarters and battery materials lab, at a construction cost of £11.84m.



If you sign by 17 September, Stage 4 starts on 27 September, the planning application goes in on 1 October and the structural frame order can be placed in April 2028.

If you don't, Stage 4 waits. Each week of delay moves the frame order by a week, and past 29 October we lose the contractor's early engagement slot and the 2028 site start with it.

The design at revision C



Views from the federated model as of 3 September. Open the live link in the project space to walk it before you sign.



What changed since rev B



Measured against the review of 2 July. The second clean room caused the area and cost increases. The carbon fall comes from replacing the concrete core.




0 m²



GIA, up 64 m²


£0.00m



Cost, up £186k


0



kgCO2e/m², down 38


0



Open hard clashes

After this signature, moving a column costs a redesign of three packages. Moving a bench costs an afternoon. We've written down which is which.

What is fixed, and what can still move



Stated per system. Changes to fixed items after signature go through the change procedure in our appointment, with a cost and date attached before any work starts.



Fixed after signature

Structural grid at 7.5 m by 9 m. Floor to floor at 4.2 m on lab levels and 3.6 m on office levels. Core and riser positions. Facade module at 1.5 m. Clean room location and its 450 mm raised floor.

Movable until 14 January 2028

Lab bench layouts, fume cupboard positions within the service spines, equipment loads up to 5 kN/m², and room data sheets. After the freeze on 14 January these become change items.

Movable until tender

Finishes, loose furniture, signage, reception joinery and the planting scheme. None of these touches the coordinated model.

Risks you carry with this approval

Planning. We rate the application as supportable after two pre-application meetings, and no architect can promise consent. The determination period for a major application is 13 weeks. Stage 4 proceeds at risk during that period, and its fee is payable if consent is refused.

Not part of this approval

Consultant appointments stay with you: structural engineer, M&E consultant, quantity surveyor and principal designer under CDM 2015. Planning and building control fees are also yours. Our fee stays as appointed under the RIBA Standard Professional Services Contract.

The two weeks after you sign



Four actions in the two weeks after your signature. Nothing else needs you until the room data freeze.



Rev C locked, same day

Joel Prenderby marks the model as the coordinated baseline and issues it to all consultants.

Consultants instructed, 20 September

Structural engineer and M&E consultant receive their Stage 4 instructions, against the signed baseline.

Stage 4 kickoff, 27 September

A weekly coordination meeting starts, with the clash report published every Friday in your project space.

Planning application, 1 October

Design and Access Statement, drawings and the energy statement go in through the Planning Portal.

Stage 4 and tender



Twenty-seven weeks from signature to contractor's return. The 13-week planning determination runs in parallel and is the one date we can't control.



DayWeekMonthQuarterSemesterYear
M9Sep
M10Oct
M11Nov
M12Dec
M1Jan
M2Feb
M3Mar
M4Apr
Planning submission
Determination, 13 weeks
Structural coordination
Facade package
M&E and clean room package
Room data sheet freeze
Tender package issued
Two-stage JCT tender
Planning1 - Oct 2

Planning submission



PlanningOct 4 - Jan 3

Determination, 13 weeks



Stage 4Sep 27 - Nov 19

Structural coordination



Stage 4Oct 11 - Dec 17

Facade package



Stage 4Oct 4 - Jan 21

M&E and clean room package



Stage 414 - Jan 15

Room data sheet freeze



TenderJan 31 - Feb 1

Tender package issued



TenderFeb 1 - Mar 24

Two-stage JCT tender



Signature by Friday 17 September



If anything in revision C is wrong, tell Joel before you sign. A correction this week costs hours. The same correction in December costs a package reissue.



Prepared by



Wanjiru Mwangi Director, Threadgold Mwangi Architects

12 Osney Mead Yard Oxford OX2 0ES wanjiru@threadgoldmwangi.co.uk

For approval by



Dr Anneke Rowsell Chief Operating Officer, Halden Ionics

Project architect: Joel Prenderby joel@threadgoldmwangi.co.uk

Sign here
En approuvant ce document, vous le signez électroniquement.

Sign off RIBA Stage 3

By signing, you approve the Stage 3 design at revision C: 3,164 m² GIA and a construction cost of £11.84m excluding VAT. You also instruct Stage 4 from Monday 27 September 2027 and the planning submission on 1 October 2027.