What you asked us for
A cellar door and barrel hall on the top block, open by harvest 2029, for no more than A$6.4m to build.
You told us the wine already sells itself in Hobart. The building has to do something else: bring people out to the Coal River Valley and keep them for two hours rather than twenty minutes.
You also asked for room for 340 barrels that holds 14 degrees without a plant room the size of the tasting room. If we have any of this wrong, tell us before you read further.
How each route answers the brief
Four things you asked for, and where the routes differ. None of them fails outright. The differences are in what each one costs you.
The numbers side by side
Construction cost from our quantity surveyor, 4 June 2027. Carbon from the federated model. Programme runs from a 5 July start to opening.
Build cost, A$m
Your limit is 6.40
Embodied carbon, kgCO2e/m²
Target is 450 or less
Months to opening
Harvest 2029 allows 20
What happens after you choose
The sequence is the same whichever route you pick. A late decision moves every date below by the same number of days.
You choose, Friday 25 June
Take route 1, 2 or 3. A change to a route is fine now and costs little. The same change after schematic design costs real money.
Schematic design, from Monday 5 July
We develop the chosen route in the model, with the structural engineer and services engineer working in it from the first week.
Council meeting, Tuesday 17 August
A pre-lodgement meeting about visitor numbers, access and the top road. We expect questions on traffic, and we'd go with an answer ready.
DA lodged, Friday 1 October
The statutory assessment period in Tasmania is 42 days, and requests for more information stop that clock. We don't promise consent, and the programme carries a margin for it.
We recommend The Long Wall
It is the only route under A$6.4m and under the carbon target, with a month in hand before harvest 2029. You give up the sheltered court of route 3. If you prefer route 2 or 3, call Imelda before 25 June and we will reissue this page for it.
Prepared by
Imelda Marrable Director, Marrable Oake Architects
41 Kennedy Lane Hobart TAS 7000 imelda@marrableoake.com.au
For approval by
Nell Tregenna and Hiro Bassett Co-founders, Fallow Rise Wines
Coal River Valley, Tasmania
Approve route 1, The Long Wall
By confirming, you approve route 1 as the design direction: 760 m² at a construction budget of A$6.18m, excluding GST, and a schematic design start on Monday 5 July 2027. Our fee basis stays as appointed.