# Dossier de pré-production Perihel Eyewear : deux jours aux Pinnacles

## Overview

### Two days at the Pinnacles, locked by 6 April

*Pre-production pack · Perihel Eyewear*

What you need to approve before we travel: the film, the locations, the crew, and what happens if the wind turns.

- Shoot: 20 and 21 April 2027
- Weather hold: 22 April 2027
- From: Daniel Lim, Quarrie Lim Pictures, Fremantle

*A lone walker among limestone spires at first light*

*Quarrie Lim Pictures mark*

## Decision

### Three approvals by Tuesday 6 April

*What we need from you*

The shot list, the cast and the three locations. Sign them off below and crew and kit confirm on Wednesday 7 April.

Everything else in this pack is for reference. None of it reopens the treatment you approved on 12 March.

If approvals slip, there are two options. We hold the crew on pencil for one more week at A$3,480, or we move to the May window, when the light comes later and the wind is less reliable. We recommend signing on time, and we would take the pencil fee over the move.

## The film

Ninety seconds, one walker, no voiceover. The lens does the arguing: glare on, glare off, and the desert comes back into focus.

## Shot list

### Frame 01, first light

*A distant figure among limestone pillars at sunrise*

### Frame 02, the glare

*A silhouette on white dunes under harsh noon sun*

### Frame 03, lens on

*A hand lifting dark sunglasses against white dunes*

### Frame 04, the water

*Calm ocean at dusk from low rocks*

## Locations

### Three locations, in shooting order

Recced on 17 and 18 March by Tess, Marek and Daniel. Base is Cervantes, two hours north of Perth: three nights, one hotel, one 4WD convoy.

### Pinnacles Desert, Nambung National Park

*Limestone spires across desert sand before sunrise*

### Lancelin dunes

*White coastal dunes under midday sun*

### Thirsty Point, Cervantes

*Low rock shelf at the edge of the ocean at dusk*

## Crew

### Who you will deal with

Daniel is your one call for dates, access and budget. The others are here so you know the names on the call sheet.

### Daniel Lim, producer

Your one call for dates, access and money. He answers from 07:00 every day until wrap.

### Tess Quarrie, director

Owns the frame and the performance. Creative notes on the day go through Daniel, so she hears them once.

### Marek Olsen, DoP

Shoots large-format 6K on anamorphic glass, with a filter pass for every product shot so glare stays honest.

### Hana Tupou, first AD

Runs the clock. Her call sheet lands at 18:00 the night before. If it differs from this pack, hers is right.

### Saffron Yeo, stylist

Five looks, locked at the fitting on 14 April. She carries your nine pairs and three spares.

### Kieran Bird, drone

Licensed remote pilot, with the park's flight zones already filed. Over 25 knots he lands and we shoot from the ground.

## Schedule

### From recce to delivery

Eleven weeks, with the two review rounds you agreed in the contract. Dates after 21 April assume we do not use the weather hold.

| Task | Start | End | Duration | Label |
| --- | --- | --- | --- | --- |
| Recce, Nambung and Lancelin | 2027-03-17 | 2027-03-19 | 5 days | Pre-production |
| Casting and look tests | 2027-03-22 | 2027-03-31 | 5 days | Pre-production |
| Production meeting and your sign-off | 2027-04-01 | 2027-04-07 | 5 days | Pre-production |
| Fitting and camera test | 2027-04-14 | 2027-04-15 | 5 days | Production |
| Travel and pre-light | 2027-04-19 | 2027-04-20 | 5 days | Production |
| Shoot days, weather hold on the 22nd | 2027-04-20 | 2027-04-23 | 5 days | Production |
| Offline edit, first assembly to fine cut, with cloud review | 2027-04-27 | 2027-05-10 | 5 days | Post-production |
| Review round 1 | 2027-05-10 | 2027-05-13 | 5 days | Post-production |
| Online, grade and mix | 2027-05-14 | 2027-05-24 | 5 days | Post-production |
| Review round 2 and delivery | 2027-05-24 | 2027-06-01 | 5 days | Post-production |

## Next

### From sign-off to first light

Five dates that matter to you. Everything between them is ours to run.

### 1. Thursday 1 April, production meeting

Ninety minutes at our Fremantle studio or on video, you choose. We walk the shot list frame by frame and settle every open question.

### 2. Tuesday 6 April, your sign-off

Shot list, cast and locations, approved in this document. Crew and kit confirm the next morning and the pencil comes off.

### 3. Wednesday 14 April, fitting

Cast, looks and all nine pairs on camera in Fremantle. You are welcome in the room. Any pair with a scratch goes back that day.

### 4. Monday 19 April, travel

Convoy leaves Fremantle at 10:30. Safety walk and pre-light at Nambung at 16:30, an hour and a half before sunset.

### 5. Tuesday 20 April, crew call 04:40

Park gate, head torches on. Daniel sends you one frame at each wrap, and rushes reach your review link by 08:00 the next day.

## Contingencies

### If the plan changes

Written down now, so nobody has to work it out at 04:40 in a car park.

### If the weather turns

Thursday 22 April is held for wind over 25 knots, rain, or smoke from a prescribed burn. Daniel makes the call by 20:00 the night before.

Using the day costs A$9,360 in crew and kit, plus accommodation at cost, and it is your cost as set out in the agreement. Unused, it costs nothing if released by 18:00 on the 21st.

### If the park licence is late

The licence was lodged on 9 March and the decision is due by 31 March. Tell us now if your legal team needs to see it.

If it has not landed by 9 April, we move the dawn frames to private dune country near Lancelin. The film survives. The spires do not, so we would ask you to look at that version again before we shoot it.

### Hours, heat and overtime

Shoot days are ten working hours, overtime from hour eleven at the rates in your agreement. Day 2 is a split day, dawn and dusk, with the crew stood down from 10:00 to 15:30. Cast rest in shade in the heat of the day and there is a medic on set.

Nobody is asked to work through a rest break to catch light, including us.

### What is being delivered

One 90-second hero film, three 30-second cut-downs, six 15-second 9:16 cuts, 1:1 versions of the cut-downs, and 40 retouched stills.

Two review rounds are included. A third is A$2,180, and we will tell you before you are in one.

### Usage, music and raw files

Licensed for worldwide digital for 24 months from first publication. Out-of-home and broadcast are a separate quote. The music track and the cast buyouts are approved by you and invoiced at cost.

Rushes are not delivered. We hold them for 12 months and can supply them for a fee.

## Sign-off

### Sign off by Tuesday 6 April

This locks the plan. It does not change the fee, the usage licence or the delivery list in your contract.

### Prepared by

**Daniel Lim**
Producer, Quarrie Lim Pictures

14 Bannister Street
Fremantle WA 6160
daniel@quarrielim.com.au

### For approval by

**Ayla Rostami**
Head of Brand, Perihel Eyewear

If you would rather walk through it first, the production meeting on Thursday 1 April is the place.

### Approve the shoot plan

By confirming, you approve the shot list, the cast, the three locations and the shoot dates of 20 and 21 April 2027, with 22 April held for weather. Crew and kit confirm on 7 April. Changes after that may carry a cost, which Daniel quotes before anything moves.