title: "Installation Update Day 6 of 11: On Track for Oct 14"
description: "Day 6 of 11: 14 rooms complete against a plan of 16, 9 snags open, and the October 14 guest opening holds. See the next five days on site."
canonical: "https://pr-110.preview.formlio.com/documents/charleston-installation-progress-report"
locale: "en"
type: "document"
lastModified: "2026-11-08"
alternates:
  fr: "https://pr-110.preview.formlio.com/fr/documents/charleston-rapport-davancement-dinstallation.md"
---

# Installation Update Day 6 of 11: On Track for Oct 14

## Update

### Day 6 of 11

*Installation update*

On track for guests on October 14. Naomi, walk rooms 201 to 208 with us Thursday at 8am, and tell us about the lobby rug by Friday.

- Updated: September 20, 2027
- Install ends: September 27, 2027
- First guests: October 14, 2027

*Guest room mid-install at dusk with furniture still wrapped*

*Salas Whitlock*

## Status

Counted on site at 5pm today by Cole Whitlock.

### Of 22 rooms complete

**14**

### Of 412 pieces placed

**287**

### Snags open

**9**

### Rooms behind plan

**2**

## One thing to know

Three vanity tops arrived cracked. Rooms 204, 207 and 211 finish on October 4, not September 27. The opening does not move.

## Against plan

Plan was 16 rooms by day 6. We are at 14. The lost time was two days of vanity rework, and the crew recovers one by Friday.

### Rooms complete, by install day

| Label | Value |
| --- | --- |
| Day 1 | 2 |
| Day 2 | 5 |
| Day 3 | 7 |
| Day 4 | 10 |
| Day 5 | 12 |
| Day 6 | 14 |

### Open snags, by trade

| Label | Value |
| --- | --- |
| Paint | 4 |
| Joinery | 3 |
| Electrical | 1 |
| Upholstery | 1 |

## On site today

### Room 212, complete

*Finished guest room with an oak bed and a salt marsh view at dusk*

### Lobby, 60 percent

*Lobby mid-install with oak reception desk and wrapped banquettes*

### Room 207, on hold

*Bathroom with an oak vanity base awaiting its stone top*

## This week

### The next five days

Crew of eight, 7am to 3:30pm. Deliveries before 10am.

### 1. Tuesday, rooms 215 to 218

Beds and joinery. Lighting scenes set the same day.

### 2. Wednesday, lobby banquettes

Four pieces, one delivery. Lobby closed to other trades until noon.

### 3. Thursday, walkthrough at 8am

You, Ana and Cole. Rooms 201 to 208, one hour. Comments go straight on the snag list.

### 4. Friday, rooms 219 to 222

Last guest rooms. Snag list reissued at 3pm.

### 5. Monday, day 11

Art and mirrors, and the lobby rug if you choose Monday. Crew leaves site at 3:30pm, and styling begins Tuesday.

## Risks

### Risks and decisions

Four open. Each has an owner and a date. One needs your answer.

### Vanity tops: owner Cole, closes October 4

Three of 22 cracked in transit. The stone yard has re-cut them from the same slab. The freight insurer pays. No cost to you.

### Your decision: lobby rug, by Friday

The sealer cure ends Monday, a day later than planned. We can lay the rug Monday at 3pm or Tuesday at 7am. We recommend Tuesday. It costs $640 in crew overtime and removes the risk of marking the floor.

### Storm season: owner Ana, reviewed daily

It is the peak of hurricane season. If the county issues a watch, we stop deliveries and move wrapped pieces off the ground floor. We lose two days at most. The October 14 date allows for one such event.

### Budget: $6,180 over the $612,400 plan

Freight and labor, 1.0 percent over. It comes out of the contingency, and $31,040 remains. Nothing else is forecast to draw on it.

## To opening

### 24 days to first guests

Install ends September 27. Everything after that is finishing.

| Task | Start | End | Duration | Label |
| --- | --- | --- | --- | --- |
| Rooms 215 to 222 | 2027-09-21 | 2027-09-24 | 5 days | Install |
| Lobby and common areas | 2027-09-22 | 2027-09-27 | 5 days | Install |
| Vanity tops re-cut and shipped | 2027-09-20 | 2027-09-30 | 5 days | Rework |
| Refit rooms 204, 207, 211 | 2027-10-01 | 2027-10-04 | 5 days | Rework |
| Styling | 2027-09-28 | 2027-10-01 | 5 days | Finish |
| Snag list closed | 2027-10-04 | 2027-10-08 | 5 days | Finish |
| Photography | 2027-10-12 | 2027-10-13 | 5 days | Finish |
| First guests | 2027-10-14 | 2027-10-15 | 5 days | Opening |