Day 6 of 11
On track for guests on October 14. Naomi, walk rooms 201 to 208 with us Thursday at 8am, and tell us about the lobby rug by Friday.
Updated
September 20, 2027
Install ends
September 27, 2027
First guests
October 14, 2027

Status
Counted on site at 5pm today by Cole Whitlock.
0
Of 22 rooms complete
0
Of 412 pieces placed
0
Snags open
0
Rooms behind plan
Against plan
Plan was 16 rooms by day 6. We are at 14. The lost time was two days of vanity rework, and the crew recovers one by Friday.
Rooms complete, by install day
Plan is 22 by day 11
Open snags, by trade
9 open, 23 closed since day 1
The next five days
Crew of eight, 7am to 3:30pm. Deliveries before 10am.
Tuesday, rooms 215 to 218
Beds and joinery. Lighting scenes set the same day.
Wednesday, lobby banquettes
Four pieces, one delivery. Lobby closed to other trades until noon.
Thursday, walkthrough at 8am
You, Ana and Cole. Rooms 201 to 208, one hour. Comments go straight on the snag list.
Friday, rooms 219 to 222
Last guest rooms. Snag list reissued at 3pm.
Monday, day 11
Art and mirrors, and the lobby rug if you choose Monday. Crew leaves site at 3:30pm, and styling begins Tuesday.
Risks and decisions
Four open. Each has an owner and a date. One needs your answer.
Vanity tops: owner Cole, closes October 4
Three of 22 cracked in transit. The stone yard has re-cut them from the same slab. The freight insurer pays. No cost to you.
Your decision: lobby rug, by Friday
The sealer cure ends Monday, a day later than planned. We can lay the rug Monday at 3pm or Tuesday at 7am. We recommend Tuesday. It costs $640 in crew overtime and removes the risk of marking the floor.
Storm season: owner Ana, reviewed daily
It is the peak of hurricane season. If the county issues a watch, we stop deliveries and move wrapped pieces off the ground floor. We lose two days at most. The October 14 date allows for one such event.
Budget: $6,180 over the $612,400 plan
Freight and labor, 1.0 percent over. It comes out of the contingency, and $31,040 remains. Nothing else is forecast to draw on it.
24 days to first guests
Install ends September 27. Everything after that is finishing.
Rooms 215 to 222
Lobby and common areas
Vanity tops re-cut and shipped
Refit rooms 204, 207, 211
Styling
Snag list closed
Photography
First guests