Salas Whitlock



Installation update



Day 6 of 11



On track for guests on October 14. Naomi, walk rooms 201 to 208 with us Thursday at 8am, and tell us about the lobby rug by Friday.

Updated

September 20, 2027



Install ends

September 27, 2027



First guests

October 14, 2027

Guest room mid-install at dusk with furniture still wrapped

Status



Counted on site at 5pm today by Cole Whitlock.




0



Of 22 rooms complete


0



Of 412 pieces placed


0



Snags open


0



Rooms behind plan

Three vanity tops arrived cracked. Rooms 204, 207 and 211 finish on October 4, not September 27. The opening does not move.
TThhrreeee vvaanniittyy ttooppss aarrrriivveedd ccrraacckkeedd.. RRoooommss 220044,, 220077 aanndd 221111 ffiinniisshh oonn OOccttoobbeerr 44,, nnoott SSeepptteemmbbeerr 2277.. TThhee ooppeenniinngg ddooeess nnoott mmoovvee..

Against plan



Plan was 16 rooms by day 6. We are at 14. The lost time was two days of vanity rework, and the crew recovers one by Friday.



Rooms complete, by install day

Plan is 22 by day 11

Rooms complete, by install day

Open snags, by trade

9 open, 23 closed since day 1

Open snags, by trade

Room 212, complete

First of the river-side rooms. Bed, joinery, lighting scenes set. Snag free as of today.


Finished guest room with an oak bed and a salt marsh view at dusk

Lobby, 60 percent

Reception joinery is in. Banquettes land Wednesday. Rug waits for the floor sealer to cure.


Lobby mid-install with oak reception desk and wrapped banquettes

Room 207, on hold

Cracked vanity top removed. Plumber and stone fitter return October 1. Everything else in this room is done.


Bathroom with an oak vanity base awaiting its stone top

The next five days



Crew of eight, 7am to 3:30pm. Deliveries before 10am.



Tuesday, rooms 215 to 218

Beds and joinery. Lighting scenes set the same day.

Wednesday, lobby banquettes

Four pieces, one delivery. Lobby closed to other trades until noon.

Thursday, walkthrough at 8am

You, Ana and Cole. Rooms 201 to 208, one hour. Comments go straight on the snag list.

Friday, rooms 219 to 222

Last guest rooms. Snag list reissued at 3pm.

Monday, day 11

Art and mirrors, and the lobby rug if you choose Monday. Crew leaves site at 3:30pm, and styling begins Tuesday.

Risks and decisions



Four open. Each has an owner and a date. One needs your answer.



Vanity tops: owner Cole, closes October 4

Three of 22 cracked in transit. The stone yard has re-cut them from the same slab. The freight insurer pays. No cost to you.

Your decision: lobby rug, by Friday

The sealer cure ends Monday, a day later than planned. We can lay the rug Monday at 3pm or Tuesday at 7am. We recommend Tuesday. It costs $640 in crew overtime and removes the risk of marking the floor.

Storm season: owner Ana, reviewed daily

It is the peak of hurricane season. If the county issues a watch, we stop deliveries and move wrapped pieces off the ground floor. We lose two days at most. The October 14 date allows for one such event.

Budget: $6,180 over the $612,400 plan

Freight and labor, 1.0 percent over. It comes out of the contingency, and $31,040 remains. Nothing else is forecast to draw on it.

24 days to first guests



Install ends September 27. Everything after that is finishing.



DayWeekMonthQuarterSemesterYear
W3813 Sep
W3920 Sep
W4027 Sep
W414 Oct
W4211 Oct
W4318 Oct
Rooms 215 to 222
Lobby and common areas
Vanity tops re-cut and shipped
Refit rooms 204, 207, 211
Styling
Snag list closed
Photography
First guests
Install21 - Sep 24

Rooms 215 to 222



Install22 - Sep 27

Lobby and common areas



Rework20 - Sep 30

Vanity tops re-cut and shipped



Rework1 - Oct 4

Refit rooms 204, 207, 211



FinishSep 28 - Oct 1

Styling



Finish4 - Oct 8

Snag list closed



Finish12 - Oct 13

Photography



Opening14 - Oct 15

First guests